How long does it take to build a hall

You will get an answer to this question from most suppliers "in three months". It's true — and at the same time the least helpful answer you'll ever hear.

3. 9. 2026 2 minutes of reading KovoSmetana
The start of the construction of a new production area for our company

You will get an answer to this question from most suppliers "in three months". It's true — and at the same time the least helpful answer you'll ever hear.

Because the assembly of the hall is the shortest part of the entire process.

Breakdown by stages

Phase How long What affects her
Demand and supply 1-3 weeks the complexity of the assignment
Project for permits 1-2 months scope, disposition
Authorization procedure 3-9 months office, authorities concerned, location
Fabrication of the structure 4-8 weeks parallel to the foundations
Earthworks and foundations 3-6 weeks geology, weather
Installation and cladding 3-8 weeks hall size
Completion and handover 2-4 weeks windows and doors, floors

Why is assembly so fast?

The steel structure is not produced on site. It arises in the workshop at the moment when excavations and concreting of the foundations are taking place on the construction site. The finished parts then arrive at the site and it is assembled.

This eliminates waiting for the concrete and masonry to mature — that is, the phase that determines the entire schedule for wet processes.

What is really delaying the construction

Authorization procedure. This is the longest and least predictable part of the whole process. Depending on the location, the scope of the construction and the number of bodies involved, this is between three months and a year. Unsolved assignment. Changing the disposition at the stage when the structure is already being produced means delays and additional costs. The time spent on the task at the beginning is returned twice. Split delivery. When the foundations are made by one company, the construction by another and the cladding by a third, downtime occurs at the interfaces. None of them are responsible for them — and they are all paid for by the investor. Weather. It mainly affects earthworks and concreting. Assembly steel structure also runs in winter.

How to shorten the deadline

  1. Start the project before you think it's time. Permission is a queue to stand in.
  2. Leave the engineering to the contractor who does it routinely. It will save weeks.
  3. Complete the assignment before production. Anything changed later is paid twice.
  4. Choose one contractor for the entire construction. There will be no downtime at the work interface.

What to say to suppliers

Don't ask "how long does it take". Ask:

  • When can you start? (production capacity)
  • What's in your delivery? (the fewer companies, the shorter the deadline)
  • Will you also provide a permit?
  • When will I be able to work in the hall? — the only date you really care about

We are general contractor with own production and assembly teams. Write to us and we will tell you a real deadline for your project, not a general number.

Services

Where to look next

Let’s discuss your project

All you need is a plot of land and an idea of ​​what you will do in the hall. We'll solve the rest together — we'll get back to you within 24 hours. And if you want to see it live first, come and see us in Uherčice.

Jaroslav Smetana Jaroslav Smetana
Managing director
Jakub Smetana, managing director of KovoSmetana Jakub Smetana
Managing director · production
Ing. Tomáš Smetana Ing. Tomáš Smetana
Managing director · marketing

What are you looking for?

Enter at least 2 characters.

Menu
Request a quote →
Call us+420 737 918 106

Choose your language

ČeštinaEnglishDeutsch
Showroom Uherčice

Booking a showroom tour

We will show you a sample hall, the construction up close and the materials we build from. The tour lasts about an hour and there is no obligation.

We will confirm your preferred date or suggest the next available appointment.
We'll get back to you within 24 hours. No spam, no newsletter.
Request a quote

Request a hall quotation

Three steps, two minutes. None of this is binding — the more you tell us, the more accurate the quote you'll get.

  1. 1 Hall parameters
  2. 2 Additional information
  3. 3 Contact
What hall do you need?
Clear height beneath the roof truss.
Hall insulation
We'll get back to you within 24 hours. No spam, no newsletter.